Adur, in numbers

Projects: Adur

Adur local authority area. Every figure carries its own date.

The local plans, investments and decisions worth following.

3 selected records checked against official sources. A plan is not a completed project; each record shows the stage its source establishes.

Southwick

Repairing the new Albion Street homes

The council reports water penetration and design problems preventing tenants moving in.

Defects under investigation; homes not habitable in the July update · evidence dated 2026-07-02

Responsible body: Adur District Council

What the source says: Engineering options and a committee report were being prepared. An initial repair estimate is not an agreed final cost.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

New council homes require repairs →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Make safe homes available to waiting tenants →

Do not repeat poor construction handovers →

Make room for homes people can afford →

Target support where disadvantages overlap →

How to track delivery →

A259 beside Sussex Yacht Club, Shoreham

Shoreham town-centre flood defences

Preparatory drainage and underground surveys precede a new flood wall and path.

Preparatory work reported; completed protection not verified · evidence dated 2026-08-21

Responsible body: Adur District Council

What the source says: The scheme involves Adur, the county, Environment Agency and yacht club. Construction and residual flood risk need separate tracking.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Preparatory work on Shoreham flood defences begins →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Use the existing flood partnership →

Target safety work where problems repeat →

How to track delivery →

Shoreham

Buckingham Park southern pavilion

The council is seeking a partner to replace poor toilets, changing facilities and café space.

Planning permission secured; partner sought in July 2026 · evidence dated 2026-07-21

Responsible body: Adur District Council

What the source says: The anticipated 2027 delivery depends on a suitable development and operating arrangement.

Next thing to establish: What is the approved cost, including ongoing maintenance?

Progress, funding and source
Cost
Not established by the evidence checked.
Funding
Not established by the evidence checked.
Area covered
Named scheme or programme area only. No official impact boundary has been matched to current wards; a nearby location is not evidence that a whole ward benefits.

No verified ward footprint is assigned.

Applications open to transform Buckingham Park southern pavilion →

Source checked 2026-10-17. A plan or announcement is not proof of completion.

Questions for the next progress report

  • Which funding is committed, and what remains conditional?
  • Which neighbourhoods are covered by an official project plan, and which benefits still need testing?
  • What is the next published milestone, and what evidence will show residents benefit?

Secure a workable future for the pavilion →

Do not repeat poor construction handovers →

Target support where disadvantages overlap →

How to track delivery →